The Corporation of the

Town of Milton

Committee of Adjustment Minutes

-
Council Chambers - In Person

The Committee of Adjustment for the Corporation of the Town of Milton met in regular session in person. All members were present except member Jayaveer.


There were no Agenda announcements or amendments.

Member Ellahi's architecture firm represents the applicant.

  • Moved bySalman Ellahi
    Seconded byTharushe Jayaveer

    THAT the Minutes from the August 22, 2024 Committee of Adjustment and Consent be APPROVED

    Carried

Agent Ken Tai provided an overview of the application.

Neighbouring Resident spoke with no objections to the proposed minor variances, however, cited concerns over drainage and flood risks.

Resident Barbara Tapper spoke with concerns relating to flooding as well as the design of the home. No objections to proposed minor variances were made.

  • Moved byChristopher Trombino
    Seconded bySalman Ellahi

    THAT the application for minor variance BE APPROVED SUBJECT TO THE FOLLOWING CONDITIONS:

    1. That a Stormwater Management Brief and Grading Plan be provided, to the satisfaction of Development Engineering, prior to Building Permit issuance.
    2. That a Building Permit be obtained within two (2) years from the date of this decision; and,
    3. That the approval be subject to an expiry of two (2) years from the date of decision if the conditions are not met, if the proposed development does not proceed and/or a Building Permit is not secured.
    Carried

Agent Shivani Khapare provided an overview of the application.

Member Ellahi required clarification of the sunroom

  • Moved byChristopher Trombino
    Seconded byTyler Slaght

    THAT the application for minor variance BE APPROVED SUBJECT TO THE FOLLOWING CONDITIONS:

    1. That a Detailed Grading Plan be provided, to the satisfaction of Development Engineering, prior to Building Permit issuance.
    2. That a Building Permit be obtained within two (2) years from the date of this decision; and,
    3. That the approval be subject to an expiry of two (2) years from the date of decision if the conditions are not met, if the proposed development does not proceed and/or a Building Permit is not secured.
    Carried

Agent Shivang Tarika provided an overview of the application. 

  • Moved bySalman Ellahi
    Seconded byTharushe Jayaveer

    THAT the application for minor variance BE APPROVED SUBJECT TO THE FOLLOWING CONDITIONS:

    1. That a Building Permit be obtained within two (2) years from the date of this decision; and,
    2. That the approval be subject to an expiry of two (2) years from the date of decision if the conditions are not met, if the proposed development does not proceed and/or a Building Permit is not secured.
    Carried

The agent provided an overview of the application. 

Member Ellahi asked for further clarification of the application. 

  • Moved byTyler Slaght
    Seconded byChristopher Trombino

    THAT the application for minor variance BE APPROVED SUBJECT TO THE FOLLOWING CONDITIONS:

    1. That a Stormwater Management Brief and Grading Plan be provided, to the satisfaction of Development Engineering, prior to Building Permit issuance.
    2. That a Building Permit be obtained within two (2) years from the date of this decision; and,
    3. That the approval be subject to an expiry of two (2) years from the date of decision if the conditions are not met, if the proposed development does not proceed and/or a Building Permit is not secured.
    Carried
  • Salman Ellahi declared a conflict on this item. (Member Ellahi's architecture firm represents the applicant.)

Applicant Surinder Shokar provided an overview of the application.

  • Moved byChristopher Trombino
    Seconded byTharushe Jayaveer

    THAT the application for minor variance BE APPROVED SUBJECT TO THE FOLLOWING CONDITIONS:

    1. That a Stormwater Management Brief and Grading Plan be provided, to the satisfaction of Development Engineering, prior to Building Permit issuance.
    2. That a Tree Protection Fence be installed on any property lines abutting the adjacent woodlot, for the length of the proposed works.
    3. That a Building Permit be obtained within two (2) years from the date of this decision; and,
    4. That the approval be subject to an expiry of two (2) years from the date of decision if the conditions are not met, if the proposed development does not proceed and/or a Building Permit is not secured.
    Carried

Agent Scott May provided an overview of the application.

  • Moved byTyler Slaght
    Seconded bySalman Ellahi

    THAT the application for minor variance BE APPROVED SUBJECT TO THE FOLLOWING CONDITION:

    1. That Site Plan Approval be granted within two (2) years from the date of decision.
    Carried

Be there no further business, the Chair declared the Hearing adjourned at 6:45 PM