THAT Council authorize a contract increase of $384,909 (exclusive of HST) to Malone Given Parsons Ltd. to complete the updates required to the Britannia Secondary Plan for a change in scope to accommodate population growth beyond the 2031 planning horizon.
AND THAT Council authorize a budget increase of $391,684 for other professional fees for the Britannia Secondary Plan funded from long-term developer debt under the terms of the existing Milton Phase 4 (West) Secondary Plan Studies Funding and Reimbursement Agreement, as summarized in the financial impact section.
AND FURTHER THAT the Manager, Purchasing and Supply Chain Management be authorized to execute the contract changes, as outlined by the purchasing by-law.